Termites:

ANTI-TERMITE TREATMENT:

1. Pre Construction

Normally the pre-Construction treatment consists of 9 stage treatment as per IS 6313 PART -2 .However commercially for smaller sites only 3 stages are been treated so this treatment is being tailor made to suit the site

SOIL TREATMENT:

The chemical emulsion (either Biflex 2.5% EC or Imidachloprid -30.5% SC or Chlorpyriphos-20% EC ) with dilution as per the concentration of Active ingredient shall be applied uniformly at the prescribed rate in all the stages of treatment

1. TREATMENT FOR MASONARY FOUNDATIONS

The bottom and the sides (up to height of 300 mm) of the excavated area shall be treated with the chemical at the rate of 5 Lit/M2 of the surface area.,The backfill earth that is in immediate contact with the foundation structure shall be treated at the rate of 7.5 Lit /M2 of the vertical surface.

2. TREATMENT OF TOP SURFACE OF PLINTH FILLING

The top surface of the consolidated earth within plinth walls shall be treated with chemical emulsion at the rate of 5 lit/m2 of the surface before the sand bed or sub-grade is laid. If the filled earth has been well rammed and the surface does not allow the emulsion to seep through, holes up to 50 to 75 mm deep at 150 mm centres both ways maybe made with 12 mm diameter mild steel rod on the surface to facilitate saturation of the soil with the chemical emulsion.

3. TREATMENT OF SOIL ALONG EXTERNAL PERIMETER OF BUILDING

After the building is complete, the earth along the external perimeter of the building should be rodded at intervals of 150 mm and to a depth of 300 mm. The rods should be moved backward and forward parallel to the wall to break up the earth and chemical emulsion poured along the wall at the rate of 7.5 l/m2of vertical surfaces. After the treatment, the earth should be tamped back into place. Should the earth outside thebuilding be graded on completion of building, this , treatment should be carried out on completion of such grading.

In the event of filling being more than 300 mm, the external perimeter treatment shall extend to the full depth of filling upto the ground level so as to ensure continuity of the chemical barrier.

DOSAGE:


1. IMIDACHLOPRID-30.5%SC (From Bayer)

Dilution 1 : 476 Ratio for making the chemical emulsion

2. Post Construction

METHOD OF TREATMENT:

1. Treatment inside the Buiding at GF

The inner walls of the building at floor and wall junction will be drilled where accessibility is present The chemical used will be from M/s BAYER INDIA

2. Treatment Outside the Building

Rodding will be done at 2 Feet span 6 inches away from the building perimeter to a depth of 10-12 inches and imidachloprid emulsion is poured into the holes to wet soil below the ground

DOSAGE:

Dilution 1 :476 Ratio for the control of termite in buildings during post construction anti-termite treatment.

Need More Information About Pest Control

# Please Call Us

About Pest Eyes

Our founder  G. Muralidar, MicroBiologist have achieved greater heights by empowering Technicians to Enerpreneur level.  He Founded PestEyes to save the Environment by adopting  Integrated Pest Management (IPM) approach.

Services

  • Pest Control
  • Termite Control
  • Rodent Control
  • Mosquito Eradicate
  • Insect Killings

Contact Us

Sri Ramakrishna Villa, No 39, Sankaradasar street,, Ramalinga Nagar, Madipakkam,, Chennai, Tamil Nadu 600091

Phone : 9884186222